Vienna, October 10, 2022 - Following the successful ground-breaking ceremonies last year, ZIMA is now setting the next milestones for the new "Attemsgarten" residential quarter and the subsidized residential project Attemsgasse 42 in Vienna's Donaustadt district with two topping-out ceremonies. Greening, urban gardening, sustainable energy sources and affordable housing are the focus of both projects: In the "Attemsgarten", a three-part building ensemble with around 240 residential units will be built on a total usable area of around 16,000 m² by 2024. At Attemsgasse 42, a total of 96 subsidized rental apartments and three commercial units will also be built together with Österreichisches Siedlungswerk (ÖSW AG) on an area of around 1,434 m².

Photos: © Matthias Schmitt / SmatthiasC.at


Last Thursday, the owners, project participants and employees of the construction companies of both ZIMA projects in Vienna-Donaustadt met for the traditional topping-out ceremony in the completed building shell. The new "Attemsgarten" residential quarter at Attemsgasse 44, a green oasis in the middle of Vienna, will be completed by 2024. It will offer future residents a conscious and sustainable lifestyle with a well thought-out urban gardening concept. Beds for the individual cultivation of vegetables or flowers as well as shady pergolas stand for closeness to nature. The 240 apartments in the three-part building ensemble have spacious balconies and terraces.

The second completed building shell at Attemsgasse 42 - in the immediate vicinity of the "Attemsgarten" urban quarter - was realized together with Österreichisches Siedlungswerk (ÖSW AG). A total of 96 subsidized rental apartments spread over eight floors and three commercial units with a total usable area of around 5,000 m² are being built here. "The joint project with Österreichisches Siedlungswerk at Attemsgasse 42 offers people with different social backgrounds a new home. The funding from the City of Vienna makes it possible to create attractive and affordable housing for as broad a cross-section of the population as possible," says a delighted Ernst Nevrivydistrict leader of the 22nd district.

Sustainable living at the highest level
Erwin BrauchartManaging Director of ZIMA Wien GmbH: "With the Gleichen celebrations, we have reached the next milestone for our important projects in Attemsgasse, in the heart of one of the most liveable and attractive cities in the world. With both projects, we want to show how sustainable residential construction for people with high standards of living quality, price and reliability can be successfully realized in the future and how inner-city coexistence can be optimally implemented."

Gerald Parzer, lead project developer at ÖSW: "The project at Attemsgasse 42 is completely geared towards high-quality and affordable housing and is therefore fully in line with our founding idea of creating attractive and affordable housing options for as broad a cross-section of the population as possible."

Thomas Behacker from the construction company PORR: "In the 'Attemsgarten' project, we are placing particular emphasis on sustainable, resource-conserving construction. We want to show how the environment in the middle of the city can be positively shaped. Because with projects like this, we are not only shaping people's living environment, but also laying the foundations for future generations."

Short distances
Both new-build projects are close to an educational campus, kindergartens and a grammar school, and the Westfield Donau Zentrum is also within easy walking distance. In summer, the Alte Donau can be reached in around ten minutes by bike. An ideal urban offer with short distances, which should appeal to young people and families in particular. Despite challenging times, both projects will be completed and handed over on schedule in spring 2024.

Fact Box

cubic meters of excavated material in total: 37.200 m³
Total number of truck journeys for excavation: 2.790
cubic meters of concrete used in total: 17.976 m³
Total number of concrete mixers required: 2.247
tons of installed reinforcing steel in total: 1.760 t
Total number of windows: 1.186
Total number of doors: 1.948
Total number of hours worked until shell completion: 123.100
General partner and project manager: ZIMA Vienna GmbH
Architect: Hawlik Gerginski Architects
Completion date: Spring 2024


About ZIMA
The ZIMA Group has been realizing real estate projects for 50 years and is one of the largest private real estate developers in the German-speaking Alpine region. The head office is in Dornbirn. Other branches are located in Innsbruck, Bolzano, Munich, St. Gallen and Vienna. Total annual output amounted to over EUR 292 million in 2021